Blog Teaser Image

2008: Steel Bridge Team Constructs a Winner

MIT CEE Fieldwork Blog

Nationals at Last!

We traveled all day Wednesday and were very tired when we arrived in Gainesville, Florida. Thursday we woke up and went to a nearby parking lot to practice. After a few practice runs and a lunch break, a friendly game of football got started (look out for a Steel Bridge IM team next year). Our practice set up was fully to scale, and we consistently got times in the 4:30s and 4:40s.

Friday was taken up by display judging and gave us a chance to see all the other teams’ bridges. There was one simple girder bridge, one unique arch bridge by Berkley, a few bridge concepts similar to ours, but the majority of bridges were more traditional trusses. A lot of us felt that the rules this year constricted design and there were only a couple truly unique designs.

Saturday we were the 10th team out of 42 to construct our bridge, which was nice because we got to see a few teams go, but still got done early in the day. After Matt gave us a beautiful rendition of the national anthem, we set up and got ready to do what we had practiced so many times.

Unfortunately, our construction went fairly poorly. While our time of 5 minutes wasn’t terrible, we dropped several nuts (each one yielding a 15-second penalty), and were penalized for a couple small dimensional violations.

Loading was successful, although the location of the load, which is determined by a dice roll, was the worst-case scenario for our bridge; we had a fairly high deflection score.

After the competition we went back to the pool to lick our wounds, then later that night we attended the awards banquet. Our score of $3.8 million gave us 21st place, with Berkley's arch bridge winning with a score of $1.9 million. The fact that one of the most unique designs wound up winning was promising for next year—hopefully more teams will try radical and original ideas.

We are confident that next year’s team can get started on the design early and earn us another trip to nationals—in fabulous LAS VEGAS!

Shipping Out

We finally shipped our bridge out to Florida; it arrived last Friday. This followed an intense week of practice, where we saw our average construction time drop from around 5:30 to about 4:20. We are confident that that time can get us a top 10 national ranking.

The team was recognized last week at the annual CEE awards dinner, where Professor Connor presented us with Swiss Army Knives. It was a very nice gesture from the department, which has generously provided us with the resources we need to keep this project alive.

We're having a team dinner tomorrow night and we fly out Wednesday for the competition, which starts Friday. Thursday we’ll have some free time to relax and maybe go through a couple practice runs of the construction sequence.

A Crowd Pleaser

Monday we went through three practice runs of our construction sequence in front of the Student Center. A crowd of thousands (or hundreds ... or maybe 20) cheered as we threw down times of 5:50, then 5:24, then 4:57. This event is always one of our favorite parts of the whole process. It gets us pumped up and lets our friends and faculty see what we’ve been spending so much time on during the semester.

We always try to play the crowd with some antics, such as Adam sitting down to read a newspaper, me doing my best LeBron James impersonation with the chalk, and Matt generally just being a clown.

We were hoping to get our time a little bit lower, but we actually had some problems with the legs. First, it was tough to get them to stand up on the uneven concrete surface, and secondly, the heat actually caused some of our connections to expand, making it difficult to get things to go together. Nevertheless, we were able to demonstrate the sequence that we have worked on so hard, and display our beautiful, slender bridge.

We are continuing to practice the construction sequence and hope to get down to a point where we are consistently under 5 minutes. If we can do this, I feel like a place in the top 10 at nationals is very possible.

Time is running out, however, and we need to ship our bridge down to Florida sometime next week. Then on the Wednesday of finals week we head down there ourselves to enjoy the sun and show the rest of the nation what the MIT Steel Bridge team is made of.

Preparing for Nationals With a May 5 Demo

Over the past couple of weeks, we’ve redesigned several aspects of our bridge in response to our performance at regionals. The consensus was that we needed to have a bridge that was stiffer and quicker to put together. For starters, we got rid of four of the 12 hangers, and placed the remaining hangers in different positions to cover all the possible load locations. This should shave about a minute off our time.

The connections in the top frame of our bridge were also completely overhauled. We now have a locking flange plate that is incredibly rigid under compressive loads and bending. We also lowered the upper frame by about an inch and a half to fit within the height restriction. Before we were over by about a quarter-inch (although this went unnoticed at the regional competition).

We’ve load tested the bridge and found that our aggregate deflection decreased by 25 percent, so we think we will be in excellent shape going into nationals. Now it’s pretty much just a matter of practicing our construction sequence.

Our welders from Boston Bridge Services have been putting in a lot of time recently, but now we think we’re pretty much done with our modifications, although there is one radical idea that we’re still tossing around. We may try it out and see what happens. I’ll keep you updated.

I really hope a lot of people can come out to the Student Center steps on Monday, May 5th at 1 p.m. to see a demonstration of the construction. Although we won’t be loading the bridge, the construction sequence is incredibly fun to watch (especially when we liven it up with a few crowd-pleasing stunts).

Regionals: Second Place!

Saturday we woke up bright and early to set up the bridge at UNH's Whittemore Arena for aesthetics judging. Eleven teams were registered for the competition, but UNH was disqualified because the team didn’t complete fabrication of its bridge (because they were so busy setting up logistics for the competition itself). To their credit, they still registered as the 11th team at regionals, making it possible for three instead of two New England teams to enter nationals. Having more than 10 teams compete in a regional competition qualifies that region to send three teams to the national competition.

Merrimack University finished fabrication of its bridge the morning of the competition and made it just in time for the judging. And we thought we waited until the last minute...

The Competition

A surprising three teams entered this year's competition with simple girder bridges, which was truly shocking under the new rules. The rules change a little each year; this year they limited the depth of the girders and increased the importance of stiffness. There were several impressive truss bridges, and an unprecedented arch bridge with a box girder deck from the University of Vermont. But our bridge idea—which can best be described as a frame-supported, cable-stayed bridge—was an original.

We were the second team to construct and load our bridge. We accomplished a construction time of 7:40, but made a couple of minor errors, which added time penalties, bringing it up to 8:15. More importantly, we made a key mistake: at the end of our construction, our bridge didn’t sit completely inside the footings. The judges added a stiff penalty to our score for the weight of our bridge.

Regardless, we went on to load test the bridge. We passed the 50-pound lateral-load test with flying colors, then began the 2,500-pound vertical-load test. Adam Talsma, Matt Pires and I began loading 28-pound weights to the deck of the bridge. By the end, we were becoming very nervous that the top member of our frame would buckle. Thankfully it did not, and we unloaded the bridge quickly after deflection measurements were taken. Our deflection was right about what we thought it would be, but we will have to come up with ways to decrease it in order to be competitive at nationals.

Of the first seven teams who competed, we were the only ones to have a bridge that didn't exceed the maximum deflection or fail completely.

The last three teams to compete—UConn, Laval and Northeastern—were all very good and we were concerned that, because of our penalties, they could all beat us. UConn turned in a good time and had a bridge that performed very well. We all breathed a sigh of relief (or in Adam's case, a scream of joy), when we discovered that we had beaten them by about 3 percent of our own score. Northeastern built their bridge very quickly with just five builders (we had six), and their deflection was 40 percent of ours, so they wound up beating us by a considerable amount. Laval, the last of the teams that we thought would do very well, suffered several costly penalties that nullified the incredible stiffness of their bridge. Laval wound up coming in 4th.

That put us in first place for construction time and second place overall, giving us a chance to compete in the national competition in Florida next month.

We’re greatly looking forward to that, but we have a lot of work to do if we want to be competitive. Keep checking back for more updates on our work.

The Paper Competition

In order to be eligible for the Steel Bridge National Competition, we had to attend the ASCE Regional Business Meeting on Friday and participate in a paper competition, which included giving a five-minute speech.

The paper topics for these things always seem to focus on topics that use nice-sounding words like “privatization” and “sustainability,” so we joke that they must put the big words on a dartboard and throw darts to select the topic. This year it landed on “infrastructure privatization.” Team member Lauren Biscombe bit the bullet, prepared the paper and speech, and wowed the judges with her thoughtfulness and poise. She came in third in the paper competition.

After the meeting, we went to UNH's engineering building to practice our construction sequence (and dance moves) a few times. On our third or fourth run-through, we were able to get our construction time down to under seven minutes, a truly remarkable feat considering the complexity of our bridge design.

Last-Minute Correction

We're leaving today for New Hampshire and the regional steel bridge competition. Last night we practiced for about three hours, after we uncovered some rules that we had previously missed. The new rules call for a floodway in addition to the river, in which no team members can step. This means that the builders who stand in "barges" in the "river" have a greater amount of work to do than we thought, because the people on land cannot reach many of the connections.

We settled on a construction sequence that is a left-to-right construction rather than a bottom-to-top construction. This way all builders are busy for the entire time. We are confident that this new sequence, which we can complete in roughly eight minutes, will give us good odds to place in the top three at regionals, and earn a trip to the national competition in Florida at the end of May.

Construction Sequence

In the final moments before spring break, the team was able to complete the fabrication of the bridge, but we discovered there were still a few kinks. Due to the hard work of our consultant, Sean Homem, MEng ’07, and our welders, Jimmy O’Donnell and Jimmy Duffy, the problems were fixed over spring break. The bridge was in tip-top shape when we returned tan and relaxed from spring break.

Yesterday the team met to go through the construction sequence, which needs to be very efficient because a major portion of the team’s final score is based on the timed construction. We started with the basic assembly procedure that takes place in the construction yard (assemblies of up to three pieces are put together, then brought out to the building site 30 feet away), then moved onto the sequence of putting the assemblies together in the building site. We have two builders working in each construction yard (an area on either side of the bridge), and two “barges,” in which people have to stand in the 13’ wide river to help put together the pre-assembled sections. Making the sequence such that no one is under or overworked during the construction process is very difficult and will take some further tweaking to make perfect. But we are confident we can get our total construction time down to less than 10 minutes, which will put us in very good position to do well at regionals.

We’ll continue to practice and tie up a few loose ends for the remainder of the week. On Friday we’ll ship up to New Hampshire to compete with a dozen other schools from New England.

Design and Build

Conceptual design began in the fall. We decided early on to go with a truss-like structure this year because the new rules emphasized stiffness over lightness. Based on some other bridges we saw at nationals last year, we came up with a few basic ideas then began to go into more detailed design. Our final product will be a sort of hybrid between a truss bridge and a cable-stayed bridge.

The first detailed design challenge was to decide what to do for the girder pieces. We wanted a section that was lightweight and would provide lateral stiffness, so we could eliminate cross-bracing. The trickiest part was to come up with a connection for the pieces that was quick to put together and also very rigid. We had some ideas for dovetail connections from bridges we saw at nationals, and were able to prototype and test a sample connection.

We began fabrication on the main girder pieces in February, and with the help of Jimmy Duffy and Jimmy O’Donnell from Boston Bridge Services, we were able to fabricate these very efficiently. The next step was to build legs for the bridge and design pieces for the upper part of the truss structure. These pieces were simpler to design than the main girder pieces and were done in the matter of a couple days, although ironing out some troubles with the connections has taken some more time.

We currently stand very close to completing the bridge. We hope to finish up this week and have time to practice before and after spring break.

Getting Started

The team works three to four times weekly and spends most Saturdays designing and building the bridge. The biggest challenge so far has been the truss. “We’ve had troubles designing an efficient truss superstructure and determining what materials to use for it,” said Tina Lai, who also said the team had put in extra time to design lightweight, stable legs for the bridge.

The 2008 National Student Steel Bridge Competition will be held on May 23-24 at the University of Florida in Gainesville.

Team Members

Seniors: Quinn Vollmert and Tracy Takemura
Juniors: Lauren Biscombe, Jose Cano, Tina Lai and Jennifer Tang
Sophomores: Matthew Pires and Adam Talsma
Alumni Mentor: Sean Homem (M.Eng. 2007)
Faculty/staff mentors: Professor Jerome Connor and Stephen Rudolph
Industry Mentors: James Duffy and James O'Donnell of Boston Bridge Associates

Photographs: Stephen Rudolph